Location: Clementi Avenue 6, Singapore
Type: HDB, Government
GFA: 169,170 m2
Floors: 40 Floors (6 Blocks)
Duration: 10 Calendars Week
Current Average (Days)
Create format and table in excel for data input. Measured by scale rule and key in the dimension one by one 8
Manually build in calculation formulae to derive quantities [Manual taking off the Reinforcement Bar] 16
Structural works [Concrete, Formwork, excavation, etc.] 15
Architectural works [Can start concurrently when doing structural works 6
TOTAL 45
Cubicost BIM Application Average (Days)
Input all data, import drawings, draw the elements to generate 3D model (Use existing 3D model from structure) 2
Automatic calculation [TRB] 5
Auto generate TAS [After TRB is done, concrete and formwork is there except remaining work like excavation, pile cap, etc.] 4
Architectural work [Can only start after TAS is done] 3
TOTAL 14
Priorities and difficulties in QS’ manual calculation

1. Time consuming to analyse and identify

2. Preparation time to set up the excel format

3. Upkeep addendums and changes of quantities without considering SMM Singapore rules implementation

Strength of software application

1. 3D view for better visualization and clarity of model designed. Able to capture missing element easily from 1 look of the building

利来国际【w668899.com】2. Software to help us to easily identify the missing elements

利来国际【w668899.com】3. Auto generation of quantities for TAS after completion in TRB with correct QS measurement rules to acquire.